email2uwf schreef op 25 augustus 2023 11:27:
Meanwhile, Dr Paul Davis, assistant professor of management at Dublin City University, said the contractor is legally entitled to make claims because the design was not complete when the project went to tender.
“Given that we didn't have a design in the first place when we actually went out to contract, there were going to be changes to the design,” he told RTÉ’s Claire Byrne.
“So what we have is €760m of claims based on the design that wasn't there. So it's understandable that that has escalated over the years.”
www.irishexaminer.com/news/arid-41212...